Environmental and social impact study (ESIS) of the 120 MW Nkok solar power plant

CLIENT

SOLEN

COUNTRY

drapeau_gabon
Gabon

FUNDING

Private - SOLEN

CONTRACTUAL SCHEDULE

2022 - 2022

PROJECT DESCRIPTION

The project comprises two components: (i) construction of a solar power plant with a capacity of 120 MW over an area of 251 ha, and (ii) installation of a 10 km long 90 KV power line linking the plant to the 225/90 kV Ntoum 2 transformer substation in Libreville province.

SCOPE OF SERVICES

  • Phase 1 : Preparation of the ESIA Terms of Reference
  • Phase 2 : Preparation of the Stakeholder Engagement Plan
  • Phase 3 : Preparation of the ESIA
  • Phase 4 : Preparation of the Resettlement Action Plan (RAP)

ROLE

Individual Contractor

PROVIDED TASKS

  • Environmental and Social Impact Assessment (ESIA)
  • Resettlement Action Plan (RAP)

FIELDS OF ACTIVITY

Energy

  • Non conventional Energy

Sustainable Development (SD) & Climate Change (CC)

  • Development of Sensitive/Forested Areas